Meetings and Timeline - Updated 3/1/2010
Project Component |
Estimated Completion Date |
FDEP Pre-App Meeting, Tallahassee, FL |
April 1, 2008 |
USACE Pre-App Meeting, Palm Beach Gardens, FL |
April 8, 2008 |
Martin County Public Workshop |
May 20, 2008 |
DEP Permit Application (JCP) |
February 3, 2010 |
DEP Notice to Proceed |
February 3, 2010 |
USACE Permit |
February 16, 2010 |
Construction |
March – April 2010 |
Biological Monitoring |
Ongoing (Dan McCarthy) |
| Physical Monitoring | Ongoing (Martin County) |
June 20, 2008 - Public Comments Posted
BTB_May_20_Public_Comments_w_County_Reply.xls